Retirement

QROPS Notification Rules

All Qualifying Recognised Overseas Pension Schemes (QROPS) schemes will have to notify HM Revenue & Customs (HMRC) of their status every five years, according to new proposals published by the tax man.

The notification rule starts from April 1, 2015 and the renotification date depends on whether a QROPS was started before or after April 1, 2010.

Post April 1, 2010 QROPS

The notification date is set five years after the date HMRC sent the scheme manager their QROPS reference number.

HMRC gives some examples in draft guidance about the new regulations:

  • If the HMRC QROPS reference letter was dated April 2, 2010 the scheme manager must renotify QROPS status on: April 2, 2015, then April 2, 2020, April 2, 2025 and so on
  • If the QROPS reference letter was dated June 15, 2012, the renewal deadlines are: June 15, 2017, June 15, 2022,  June 15, 2027 and so on

Pre April 1, 2010 QROPS

HMRC wants these QROPS to renotify their status before the 10th anniversary of the QROPS reference letter.

A table of renotification dates was published with the draft guidance:

Date of HMRC QROPS reference letterFirst Renotification date
April 6, 2006 - May 31, 2006April 30, 2015
June 1, 2006 - July 31, 2006May 31, 2015
August 1, 2006 – September 30, 2006June 30, 2015
October 1, 2006 - November 30, 2006July 31, 2015
December 1, 2006 - January 31, 2007August 31, 2015
February 1, 2007 - March 31, 2007September 30, 2015
April 1, 2007 – May 31, 2007October 31, 2015
June 1, 2007 - July 31, 2007November 30, 2015
August 1, 2007 - September 30, 2007December 31, 2015
October 1, 2007 - November 30, 2007January 31, 2016
December 1, 2007 - January 31, 2008February 28, 2016
February 1, 2008 - March 31, 2008March 31, 2016
April 1, 2008 - May 31, 2008April 30, 2016
June 1, 2008 - July 31, 2008May 31, 2016
August 1, 2008 - September 30, 2008June 30, 2016
October 1, 2008 - November 30, 2008July 31, 2016
December 1, 2008 - January 31, 2009August 31, 2016
February 1, 2009 - March 31, 2009September 30, 2016
April 2009 1, - May 31, 2009October 31, 2016
June 1, 2009 - July 31, 2009November 30, 2016
August 1, 2009 - September 30, 2009December 31, 2015
October 1, 2009 - November 30, 2009January 31, 2017
December 1, 2009 - January 31, 2010February 28, 2017
February 1, 2010 – March 31, 2010March 31, 2017

If a QROPS fails to notify their status to HMRC, the scheme can be excluded – failing to notify includes an incomplete notification